Reykjavík will reopen Naustin, a short city-centre street between Hafnarstræti and Tryggvagata, as a shared street in December, in line with the approved traffic plan for the Kvos area. The project, run jointly by the city and the utility Veitur, combines a rebuild of the street surface with an upgrade of the utilities beneath it. The street is planned to be a shared street at first and later a pedestrian street.
What changes on the street
The new step-free surface recalls classic Icelandic knitting and is based on a pattern called “Riddari” designed by Védís Jónsdóttir. The street will have planting beds with trees and varied vegetation, and a small stage that serves both as a bench and as a venue for events on public holidays. The whole street space will be heated with snow melting. Landmótun designed the street space and Lota the lighting, with lamp posts that recall ship masts and spotlights that light the stage during events. The lighting also highlights the pale surface and increases safety for passers-by. VBV handled the engineering design.
Below the surface
Utility pipes were renewed and a dual drainage system was installed, which helps remove surface water from the area in heavy rain. The dual sewer is connected to the existing system in Tryggvagata and Hafnarstræti. The works include new cold water and district heating pipes, and street lighting with new cables, poles and lamps. Car traffic is closed during construction, while pedestrian access to properties and entrances is to be ensured throughout.
Timeline
The estimated construction period runs from May to December 2026.
| Month | Step |
|---|---|
| April | Kick-off meeting on 28 April |
| June | Fences put up, asphalt removed |
| August | Main sewer and water pipes laid; hot-water connection days on 27 August and 3 September |
| September | District heating completed; lamp posts put up |
| October | Snow melting laid, paving started, work begun on the west side |
What happens next
Paving is under way, and the knitting pattern has started to appear on the south side of the street. The city says the work will be completed in December.